In 1999, Baxter Healthcare, a USA based manufacturer of IV bags, tubing, and bags for dialysis equipment, set a team the task of sorting out problems in its Mountain Home, Arkansas plant’s cell separating division. The team determined the product's takt time - how long it takes to make it - and compared it with how often a customer buys it. It was established that a customer buys a cell separator every 40.4 seconds. Each individual step on the line was analysed to find that some people had 30 ...