A team working on a project involving and treatment of potentially hazardous wastewater in the US had been instructed by the Design Manager not to consider the moving of the facility to a new location. A VE study revealed that by moving the facility to a new location, and changing the original concept of using horizontal tanks set below ground level in a pit to using vertical tanks mounted at ground level, would more than double the facilities capacity without increasing the footprint. Managemen...